Short answer
- WPS is the Welding Procedure Specification: the written instructions for making a particular weld.
- PQR is the Procedure Qualification Record: the record of a test weld made and tested to prove that the procedure produces a sound weld.
- WPQ is the Welder Performance Qualification (sometimes written WPQR, or “welder qualification record”): the record showing a specific welder passed a test and is qualified to weld within certain limits.
Put simply, the PQR proves the procedure works, the WPS tells welders how to follow it, and the WPQ shows that a given welder can do it.
WPS: the recipe
A WPS is a document that describes how a weld is to be made. Depending on the code, it normally covers items such as:
- The welding process (for example SMAW, GMAW, GTAW)
- Base metal type and thickness range
- Filler metal and, where relevant, shielding gas or flux
- Joint design
- Welding position
- Preheat and interpass temperature
- Electrical characteristics, such as current range and polarity
- Travel speed, where specified
- Post-weld heat treatment, if required
Welders and inspectors use the WPS on the job. If the actual welding is done outside what the WPS allows, the weld may not be acceptable.
PQR: the proof
A PQR records what actually happened when a test weld (a “procedure qualification test”) was made: the real parameters used and the results of tests on the finished sample. Tests commonly include bend tests and tensile tests, and may include others such as impact (toughness) tests or macro-etch examination, depending on the code and the job.
The PQR is basically the evidence behind the WPS. Under codes that require qualification by testing, a WPS must be supported by a PQR (or in some cases more than one). One PQR can often support several WPSs, if their variables fall within what the PQR qualifies.
WPQ: the welder’s qualification
A WPQ documents that an individual welder made a test weld that met the acceptance requirements, using a given process, material, thickness, position and so on. The welder is then qualified to weld within the range those variables cover. The 6G pipe welding test is a common example. Tests are often visually inspected and then bend-tested or radiographed, depending on the code.
The WPQ stays with the welder, but is typically tied to an employer or has continuity requirements. Qualifications may lapse if a welder does not use the process for a certain period, and some codes have rules for how this is tracked.
How the three fit together
- A company writes a WPS for the weld it needs to make.
- A test weld is made and tested, and the results are recorded on a PQR. The WPS is supported by that PQR.
- Each welder who will work on production welds takes a qualification test following the WPS, and the results are recorded on a WPQ.
- On the job, the welder follows the WPS, and the inspector checks that the work matches it.
If the job is welded with a different process, material, or outside the qualified ranges, new qualification may be needed.
Prequalified procedures
Some codes, notably AWS D1.1 for structural steel, allow certain WPSs to be treated as prequalified, meaning that if the procedure stays within defined limits, it can be used without a PQR. These WPSs still need to be written down, and welders still need to be qualified. The conditions for prequalification are specific, so confirm them in the applicable code rather than assuming a procedure qualifies.
What an inspector checks
Inspectors typically verify that:
- A WPS exists for the weld and is approved for the job.
- The WPS is supported by a PQR, or is prequalified under the code.
- The welder holds a current WPQ covering the process, material, thickness and position being welded.
- Actual conditions, such as filler metal, preheat and joint fit-up, match the WPS.
This is one part of the broader visual inspection process, which starts before the arc is struck.
Common mix-ups
- WPS vs PQR: the WPS is the instruction, the PQR is the test record. People sometimes mix them up because they are often filed together.
- WPQ vs WPQR: terminology varies by code and region. ASME Section IX uses the term WPS/PQR for procedures and WPQ for welders, while some European and ISO-based systems use WPQR for the procedure qualification record and WPQ or welder qualification certificate for the welder. If you are working to a particular code, use its terminology.
- Welder qualified is not the same as procedure qualified. A qualified welder can still produce a bad weld if the procedure is wrong, and a good procedure doesn’t help if the welder is not qualified.
Always check the requirements of the code or contract that applies to your project, such as AWS D1.1, ASME Section IX or ISO standards.